Consolidation Parameters

In consolidation analysis (set in the frame "Settings") the bottom window in the frame "Analysis" allows us to enter consolidation parameters. 

The first construction stage of calculation represents only geostatic stress at initial time of construction. Top and bottom interface of consolidated soil layer and direction of water outflow from this layer (upwards, downwards and both downwards and upwards) is entered in the first construction stage.

The program allows us to draw a time course of settlement (graph on the right of the desktop) according to relevant theory of settlement. The vertical axis shows degree of consolidation U [%], on the horizontal axis is shown time of settlement t [days].

Frame "Analysis" - primary geostatic stress (first construction stage)

In other construction stages time of stage duration and load action are entered. Program allows for choosing from two options of load acting: entire load introduced at the beginning of stage or load linearly increases during stage duration. The calculation is then launched from the first construction stage to the construction stage where "Overall settlement" is checked (may be checked in whatever stage except first one).

Frame "Analysis" - consolidation (other construction stage)

Example: determine settlement from surcharge after 5 days, 1 month, 1 year and 5 years?  Enter construction stages according to following scheme:

1. stage

Only geostatic stress

2. stage

Surcharge, time: 5 days

3. stage

No changes, time: 25 days

4. stage

No changes, time: 335 days

5. stage

No changes, time: 1460 days

6. stage

Check option "Overall settlement" and run the calculation